New Gretna Bin 05/14/09 4:30:35 PM
| These images are of the ongoing construction of the new bin at Gretna. The first image is the start of the digging of the foundation for the footing, the footing is between 4 to 4 1/2 feet deep.
|
| The 2nd image shows the packing and measureing of the footing.
|
| This last image is showing the formation of the rebar that is being laid in the footing. Just one more step closer to pouring the concrete. Construction work is on schedule and we are looking forward to filling the new bin during wheat harvest.
|
|