Gretna Bins(cont)
Gretna Bins (cont.) 
Gretna(cont.)  06/24/09 4:32:29 PM

This is the bin after 2 days of construction, starting from when the roof was added.  This shows 9 rings have been added out of 17.  The workers are averaging 2 rings a day.

Here we are at 12 rings out of 17.  We will be able to dump in the new bin for the 2009 wheat harvest!!!

The workers are digging out the footing for the overhead load out tank.  There is a footing on each side of the current dump pit.  Construction will continue on this part during the wheat harvest, but it will not interfere with the dumping of wheat into the bin.

 